[{"label":"Home","url":"https:\/\/www.pbo-dpb.ca\/en"},{"label":"Publications","url":"https:\/\/www.pbo-dpb.ca\/en\/publications"},{"label":"Canada\u2019s Eastern Corridor High-Speed Rail: A Cost Analysis using Global Data","url":"https:\/\/www.pbo-dpb.ca\/en\/publications\/RP-2627-009-C--canada-eastern-corridor-high-speed-rail-cost-analysis-using-global-data--train-grande-vitesse-corridor-est-canada-analyse-couts-aide-donnees-mondiales"}]
Report

Canada’s Eastern Corridor High-Speed Rail: A Cost Analysis using Global Data

Published on October 1, 2026 PDF(opens a new window)

This report responds to a request from the Standing Senate Committee on National Finance to provide an analysis of the Government’s proposed high-speed rail line between Toronto and Quebec City.

Summary

The Government of Canada has proposed to build a high-speed rail (HSR) line along the Toronto-Quebec City corridor. The project has been mandated to Alto, a Crown corporation, in partnership with Cadence, a consortium that was chosen to design, build and operate the line.

The Government estimates that it will cost $60–$90 billion (2024 dollars).

Based on analysis of international construction experience and assumed characteristics of the proposed Canadian route, PBO estimates that the baseline route (excluding Kingston) could cost between approximately $75 billion and $113 billion to construct. This range reflects the considerable uncertainty inherent in large-scale rail infrastructure projects.

This analysis does not scope in the Government’s announcement on June 22, 2026, that it may amend its preferred route to pass through Kingston. Such a route change is expected to increase uncertainty beyond the baseline route due to the counter-balancing effects of easier geography for construction but higher density of regional populations and greater ecological sensitivity, which are discussed in general terms in this report.

Tunnels and elevated structures are major construction cost drivers. International evidence indicates that each additional kilometre of tunnel will add $169 million to the total cost of this project, with a range of $142 to $196 million, while an additional kilometre of elevated structures will add $153 million to this project, with a range of $132 to $175 million.

The Canadian Shield represents an important engineering challenge. Approximately 130 km between Ottawa and Peterborough could encounter Shield terrain. The report assumes extensive rock cutting, grading and filling would be required to accommodate 300 km/h trains – making the cost comparable to, though lower than, that of elevated structures.

Construction to the Island of Montréal is expected to require significant tunnelling. This analysis assumes approximately 15 km of tunnel would be needed to connect Laval and Montréal, while the Montréal–Ottawa and Montréal–Quebec City sections are expected to encounter comparatively less difficult terrain.

Real HSR construction costs have risen internationally over time. Each additional year in this project's start date is associated with construction costs approximately $1.5 billion more, with a range of $1.1 to $2.0 billion, even after accounting for tunnels and elevated structures.

Institutional and project-management risks have been assessed to be more important than engineering risks. After controlling for observable project characteristics, U.K. and U.S. projects have cost roughly 4.5 times as much as European projects, although the estimate is based on only three observations. Factors associated with cost escalation can include land acquisition and permitting problems, litigation, design changes, non-standardised designs and weaknesses in project-management capacity.

Recent federal legislation may reduce these risks for Canada. Bills C-5 and C-15 are intended to streamline approvals, impact assessment and land acquisition. The report concludes that these measures may reduce—but do not eliminate—legal, permitting and schedule risks.

Construction would provide a modest near-term economic stimulus. For the Ottawa–Montréal segment, PBO estimates construction would raise real GDP by approximately $1.8 billion in 2029, increasing to $2.0 billion by 2033, while employment gains would rise from about 4,300 to 9,000 jobs. These are annual level effects, not cumulative gains, and exclude potential productivity benefits once HSR becomes operational.

This report is the first of a two-part assessment of the viability of the proposed HSR line; a subsequent report will examine whether projected ridership is sufficient to support the system's operations.[^1]

Background

The Government of Canada has proposed to build a high-speed rail (HSR) line along the Toronto-Quebec City corridor. The project has been mandated to Alto, a crown corporation, in partnership with Cadence, a consortium that was chosen to design, build and operate the line.

The Government has indicated that the project is expected to cost between $60 billion and $90 billion (2024 dollars[^2]. That cost is highly dependent on the specifics of the route since HSR lines have constraints regarding the rate of curvature – both horizontal and vertical – of the tracks that the train can safely and comfortably traverse. Although the details of the proposed route have not been made public, a generalised view from Alto (Figure 1) nonetheless shows that it goes through some difficult terrain. In particular, the Canadian Shield covers a significant part of the area between Ottawa and Peterborough.

Reproduced with permission (September 11, 2026).

Reproduced with permission (September 11, 2026).

Also challenging are the dense urban areas around major cities. For example, as illustrated, the connection between Montreal and Laval will require a new track since there is nothing available that could be utilised by high-speed trains. Public comments suggest that a tunnel of significant length is under consideration.

This report examines the physical construction challenges of the baseline proposed route and attempts to account for the cost of building a HSR over such terrain. It does so primarily by drawing from cost profiles of high-speed rail projects previously undertaken around the world. Specifically, PBO analysed a database that includes physical and cost information from 94 HSR lines that are either completed, or nearing completion. Data on 57 of them are sufficiently detailed to allow closer analysis of specific components relevant to the Alto project, such as tunnels, elevated tracks and the date at which construction began.[^3]

While there has been a wide variation in overall construction cost of past HSR projects, common geographic realities provide strong indicators of final cost.

Those results make it possible to develop an indicative estimate of Alto’s baseline route construction cost based on inferred characteristics of the proposed route.

This analysis does not scope in the Government’s announcement on June 22, 2026, that it had directed Alto to develop a plan to assess a Southern route option between Peterborough and Ottawa that includes a potential stop in Kingston (illustrated in Figure 1; Box 1; herein referred to as the Kingston amendment or route). The government has not yet released a revised construction cost estimate for this route. Such a route change would increase uncertainty regarding the final cost beyond the baseline route costing per our findings below. Below we also provide a descriptive summary of potential cost challenges of amending the baseline route to include Kingston.

This report also discusses key uncertainties and risks that could affect both the Government's estimated cost and the estimates presented herein.

While many, if not most, HSR systems around the world do not achieve operational profitability, a few that do are very profitable.[^4] The motivation for HSR projects typically includes the economic benefits to business and pleasure travellers of shorter, more predictable, and ideally cost-effective, travel as compared to travelling by road or air – as well as the environmental benefit of reducing fuel consumption and infrastructure depreciation accordingly. PBO is currently compiling information about regional travel volumes across these different modes of transport as the basis for this subsequent study.

Project costs

Previous cost estimates for an HSR line in the Toronto-Quebec City corridor have varied widely, ranging from $14 billion to $80 billion, as shown in Table 1. The breadth of this range reflects substantial differences in the scope and design of the projects being assessed. Factors have included the geographic obstacles within the line, the distance and population density of the route, operating and design speeds, the use of existing infrastructure, and the amount of tunnelling, bridging and elevated construction required. The estimates have also reflected different completion dates, making comparisons sensitive to assumptions about cost of materials and duration of the project.

For example, the GEPL estimate applied only to the Toronto–Montréal segment, while other estimates cover a larger portion of the Toronto–Quebec City corridor. EcoTrain assumed that high-speed trains would share some existing tracks with commuter services, thereby limiting the amount of new infrastructure required. By contrast, Cadence contemplated a new tunnel between Laval and Montréal, contributing to a difference of more than a factor of two between the two estimates.

Consequently, the estimates shown in Table 1 should not be interpreted as alternative cost assessments of an identical project. Rather, they illustrate how route selection and design choices can materially affect total capital costs. The international analysis that follows better addresses this comparability issue by expressing project costs on a common per-kilometre basis and examining several observable cost drivers.

International Cost Comparison

Comparing construction costs across international HSR projects requires a standardised measure. A commonly used metric is construction cost per kilometre of track.

Although the proposed HSR line has often been described publicly as a 1,000-kilometre route, its actual length may be shorter. The driving distance from Toronto to Quebec City via Montréal and Ottawa is less than 850 kilometres. Moreover, the analysis focuses on new HSR-capable track, whose alignment would generally be more direct than the existing road network because high-speed trains require fewer and broader curves. We therefore use 850 kilometres as an upper-bound assumption for the length of new track. On this basis, the Government’s estimated total cost of $60 billion to $90 billion is equivalent to approximately $71 million to $106 million per kilometre, expressed in 2024 dollars.

This can then be compared to actual (ex-post) costs observed for 94 comparable systems (dedicated HSR lines) in other jurisdictions, as shown in Figure 2.[^5] The source of those data is the Transit Cost Project under New York University Marron Institute of Urban Management.[^6] That group built the database in an effort specifically to understand factors that contribute to varying project delivery costs across countries.

Construction costs vary considerably across projects in the international sample. Alto’s estimated total falls near the middle of the international sample (Figure 2).[^7]

$0$50$100$150$200$250020406080100Number of projectsMedian: $82mAltoprojectionHigh $106m,Low $71m70th percentile ($106m)Chūō Shinkansen,Japanese maglev train ($567m/km)British HS2 ($877m/km)
Global costs of HSR track per kilometre (2024$ millions, CAD)

Transit Cost Project (NYU Marron Institute of Urban Management).

Transit Cost Project (NYU Marron Institute of Urban Management).

In 2024 Canadian dollars, converted from inflation-adjusted 2023 PPP in other countries.

Notably, the cost distribution exhibits a pronounced skew toward the upper end, with costs rising to $187 million per kilometre at the 90th percentile (Table 2).

Of the 94 HSR lines included in this initial survey, 57 projects had sufficiently detailed and consistent documentation to analyze the relationship between project characteristics and construction costs. The characteristics examined included design features (the presence of tunnels or elevated structures), the year in which construction began, and geographical region (Table 3). Collectively, these factors accounted for just under 70 per cent of the variation in construction costs per kilometre. Details on results and methodology are presented in the Appendix.

The presence of tunnels or elevated structures was associated with substantially higher average construction costs per kilometre relative to at-grade construction. A 1 percentage-point increase in the share of tunnels was associated with costs that were 1.6 per cent to 2.2 per cent higher. For elevated structures, costs were 1.6 per cent to 2.0 per cent higher.[^8]

More recent construction start dates were associated with significantly higher inflation-adjusted costs per kilometre (Appendix and Figure 3). Each additional year was associated with an estimated cost increase of 1.5 per cent to 2.7 per cent. This relationship persists after controlling for the presence of tunnels and elevated structures: the estimate in the Appendix accounts for tunnels and elevated structures, while the trend line in Figure 3 does not. The bottom line is that real construction costs have increased over time independently of these measures of project complexity.

88080019741979198419891994199920042009201420192024Rest of WorldUK / USAsiaEuropeFitted trend
Real construction costs per kilometre by construction start year

Transit Cost Project (NYU Marron Institute of Urban Management).

Transit Cost Project (NYU Marron Institute of Urban Management).

Costs are measured at 2023 purchasing power parity and converted to 2024 CAD. They are represented on a logarithmic scale.

Train speed and the annual rate of construction (in kilometres per year) were not found to have a significant association with costs.[^9]

However, costs were significantly higher for projects in the United States and the United Kingdom relative to those in other regions, mainly due to the very high costs reported for two observations: California’s Initial Operating Segment between Merced and Bakersfield, which has suffered from problems in acquiring land rights and permits along the proposed route, and the High Speed 2 line between London and Birmingham in the United Kingdom, which has been affected by project design and project management shortcomings. After controlling for the other characteristics in the model, estimated costs in the U.K. and U.S. were roughly 4.5 times those in Europe. That said, the range is wide, from about 3 to 7.3 times, reflecting how few U.K./U.S. observations are available to estimate this precisely.

Beyond these specific cases, some research has pointed to a more generalised set of factors contributing to higher construction costs in the U.K. and U.S., including project delivery issues related to procedural hurdles in land and permitting, litigation exposure, non-standardised designs, and limited technical capacity within owner agencies.[^10]

Given the institutional similarities between the U.K., U.S. and Canada, an HSR project in Canada may be at risk of similar cost escalation pressures. Construction costs for certain infrastructure projects in Canada have been observed to rise at a faster rate than in comparator countries.[^11]

Both the fast-tracking of large projects through Bill C-5 (One Canadian Economy Act, June 26, 2025) and the High-Speed Rail Network Act, enacted through Bill C-15 on March 26, 2026, aim to mitigate some of these potential difficulties related to project delay. The legislation declared that the network is to work for the general advantage of Canada, deemed the required line-location approval as given, and consolidated review under a single Impact Assessment Act process. It also altered land acquisition, including a right of first refusal for Alto and amended the federal Expropriation Act.

While the passage of those bills can be expected to have diminished legal risks, the prospect of court challenges or other litigation remain risks to construction timelines. Moreover, even if the bills survive legal challenges, it cannot be assumed that they have correctly addressed the potential drivers of cost escalation.

While this report does not estimate the cost of a Kingston route as announced on June 22, 2026, it should be noted that the more sensitive nature of the Kingston ecology as well as its denser population and later planning start vs the baseline route are all significant risks that may place the Eastern HSR project at greater risk of U.K. and U.S. style cost escalation (Box 1).

If the rail line is roughly equally direct within each corridor (Ottawa-Peterborough and Ottawa-Kingston-Peterborough), it could add approximately 50 km to the route. The Kingston route is more level and avoids more of the Canadian Shield.

The change may have important implications beyond adding distance. The Frontenac Arch Biosphere – one of Canada’s UNESCO-designated Biosphere Regions – is south of the baseline route but could be traversed by a Kingston route. This would require greater mitigations (remedial actions such as wild-life corridors, environmental restoration, etc.) to avoid further degrading an area already described as stressed (Hyett, 2026).[^12] Other areas close to the St Lawrence River along the potential Kingston route are also considered ecologically vulnerable.

Moreover, a change to include Kingston would route the line through more settled areas necessitating considerably more right-of-way and land acquisitions. It is also likely to pass through indigenous lands and traditional territories – requiring greater consultation and consideration.

Legal challenges related to environmental and stakeholder opposition were observed to cause significant planning and project delays in the Californian project, that made it notably higher cost than other global HSR projects. Regarding ridership, while the roughly 180,000 people in the Kingston Census Metropolitan Area would draw additional traffic onto the line, the increased travel time between major cities vs the baseline plan would likely offset potential ridership gains of a Kingston stop.

Cost estimate

The results of the preceding international analysis can be used to derive an indicative cost range for the proposed HSR line in Canada.

From the estimated results, PBO calculates a base cost for Canada’s HSR of $88 million to $133 million per kilometre of track ($75 to $113 billion in total, $2024). PBO also calculates that each additional 1 km of tunnelling would increase the estimated cost by $169 million ($142 to 196 million), while each additional 1 km of elevated structures adds $153 million ($132 to $175 million).

In order to assess construction parameters of the baseline route, PBO issued a number of information requests to relevant government entities. PBO supplemented these requests with modest assumptions on project parameters as necessary for estimation, such as the length of new tunnels and elevated track, as well as the expected start date of construction.

Since elements of this planning information have not been made public, and remain subject to revision,[^13] PBO also took steps to ensure that confidential information respecting route planning could not be surmised from the results of our analysis. As such, we describe general characteristics that we used to estimate the baseline route costs in Figure 1.

Between Montreal and Quebec, the path follows the St Lawrence lowlands and PBO assumed it to have little requirement for viaducts – though bridges will be needed in a number of places. In contrast, we assess that the connection between Laval and Montreal would require tunneling through roughly 15 kilometers under Mount Royal.

The Montréal–Ottawa segment is expected to be relatively straightforward because it would largely traverse the lowlands surrounding the Ottawa River. Except for the potential tunnel in Montréal, its terrain is broadly comparable to that encountered by European rail lines crossing relatively flat countryside.

The Ottawa–Toronto segment would likely be more challenging. Between Ottawa and Peterborough, excluding the proposed diversion toward Kingston shown in Figure 1, the route would cross a substantial portion of the Canadian Shield. Accommodating trains operating at 300 km/h would likely require significant rock excavation and grading to meet high-speed rail alignment requirements.

The model described in the Appendix does not explicitly include rocky terrain or frequent bedrock outcrops as project characteristics. Some of their effects may be reflected in the base cost per kilometre and the regional variables, which capture differences in construction conditions not explained by tunnels and elevated structures. However, given the length and potential complexity of this segment, its terrain can be gauged by reference to Highway 7. The portion of Highway 7 between Perth and Marmora crosses approximately 130 kilometres of the Canadian Shield and is used here as indicative of the length of the proposed route that could encounter similar conditions.

Constructing the line through this terrain is assumed to involve cutting through bedrock outcrops and filling in small and medium-sized depressions rather than building elevated structures along the entire segment. To reflect these costs in the model, 1.3 kilometres of construction through the Canadian Shield is treated as equivalent to one kilometre of elevated structure. On this basis, the estimated 130 kilometres of Canadian Shield terrain is represented by 100 kilometres of elevated structures.

Using model parameters of 15 kilometres of tunnel, 100 kilometres of elevated structures, a start date of 2029, and assuming cost efficiency comparable to that typically observed in Europe,[^14] PBO estimates a range of $88 to $133 million per kilometre. This is in the upper part of the international distribution, approximately between the 53rd and 76th percentiles (Figure 2).

The baseline factors described above do not consider: (a) prediction uncertainty of the model; and, (b) uncertainty in the estimated parameters. For (a), we use a confidence interval that is expected to capture the correct value 5 out of 6 times. But since this is a new build for Canada, we judge that the risk is more likely that the project will go over budget rather than under. As such, the upper end of the range from $88 million is $133 million per km ($113 billion in total from a central estimate of $75 billion). For (b), reflecting PBO’s view that it is more likely that non-engineering issues will lead to budget overrun, we report a symmetric confidence interval around the estimated costs of $169 million per km of tunnel ($142 to $196 million), $153 million per km of elevated structure ($132 to $175 million), $1.5 billion per year ($1.1 to $2.0 billion) for each later start year.

Indeed, in scenarios where Bills C-5 and C-15 are not sufficient to contain costs related to process issues (e.g., environmental or stakeholder challenges, etc.) as was observed in the United States, and/or management-related delays extended the project, as was observed in the United Kingdom, costs could rise significantly beyond the PBO-estimated range. The difference between this adverse scenario and the reference scenario primarily reflects institutional and cultural factors, more so than geographic and technical factors, as the cost overruns observed in the U.K. and U.S. are seen to be largely unrelated to engineering challenges.

Economic impacts

In addition to its direct costs, construction of the proposed HSR line is expected to have an economic impact during the project phase. To estimate this impact, PBO applied its infrastructure investment multiplier framework using the methodology developed in its latest report on investment multipliers.[^15] This analysis focuses exclusively on the Ottawa-Montréal segment of the line as it is the only segment scheduled for construction within PBO’s medium-term assessment horizon, namely from 2029 to 2033.

The HSR project would increase aggregate demand in the economy during construction but would not add capacity until construction is completed and the line is in service. PBO’s multipliers estimate that when the economy's productive capacity is held fixed for the duration of construction, each dollar of construction spending is estimated to raise real gross domestic product (GDP) by approximately 80 cents in the first year of construction, rising to 90 cents by the fifth year (assuming that the economy is not at full employment when construction commences).

Applying these multipliers to an assumed constant annual spending profile, PBO estimates (Table 4) that construction of the Ottawa-Montréal segment of the line would:

  • Increase the level of real GDP by approximately $1.8 billion (0.07 per cent) in the first year of construction (2029), rising to $2.0 billion by the fifth year.
  • Increase employment by approximately 4,300 persons in the first year and 9,000 persons by the fifth year.

These estimates represent impacts on the level of GDP and employment relative to PBO's June 2026 Economic and Fiscal Outlook baseline. The impacts are not cumulative (i.e., should not be added over the five years).

In addition, they do not account for how the construction spending is financed (through higher taxes, reduced spending elsewhere, or higher deficits) or potential spillover effects not captured in PBO’s multiplier framework. They also do not reflect potential productivity gains or other impacts that may arise only once the line is operational.

These estimates should be seen as high level and directional, based on past infrastructure flow throughs and subject to uncertainty from several factors. For example, if the Canadian economy is operating close to its capacity, the HSR project could displace other construction activity rather than generating new activity, reducing the net impact. A different spending profile could also shift the timing and size of the estimated impact.

Appendix

To assess the impact of several potential cost drivers across an international sample of HSR projects (n=57), we estimated the following regression model:

The dependent variable $\hat{y}$ represents the estimated cost per kilometre (in logarithms), $\overline{\text{tunnels}}$ and $\overline{\text{bridges}}$ represent the proportion of each rail line consisting of a tunnel or elevated structure, respectively, and $\overline{\text{start date}}$ represents the year in which construction began, relative to 2023. The model also included indicator variables to control for differences across geographical regions (Asia, United States/United Kingdom, and the rest of the world, with Europe as the reference region). $\hat{\varepsilon}$ represents variation in cost not explained by the variables included in the model.

Equation coefficients $\hat{\beta}$ were estimated as follows:

To estimate the cost of the proposed HSR line in Canada, PBO selected values for $\overline{\text{tunnels}}$, $\overline{\text{bridges}}$ and $\overline{\text{start date}}$ based on assumptions outlined earlier in the report: i.e., $\overline{\text{tunnels}}$ = 15/850, $\overline{\text{bridges}}$ = 100/850. The $\overline{\text{start date}}$ is set to 2029-2023 as per the current schedule for the Montreal to Ottawa segment.

To generate a reference estimate, regional indicators were set equal to zero so that the result reflected the level of cost efficiency typically observed for projects in Europe, controlling for project complexity and start date.

In the adverse scenario, the indicator variable for the United Kingdom/ United States region was set equal to 1 to incorporate the estimated cost premium in those jurisdictions.

Uncertainty in the estimation can be gauged by bootstrap replication.

Using a bootstrap methodology, an upper-bound cost with 16 per cent tail probability would give a total cost $115 billion (versus $113 billion using the parameters of Table A1). Moving to an upper-bound cost with 2.5 per cent tail probability gives $243 billion. This implies that based on these international experiences, there is a 1 in 40 chance that costs would reach or surpass a total of $243 billion. The residual distribution of that bootstrap is skewed to right. This underpins PBO’s use of an asymmetric distribution of costs – including the observation that this project is a first for Canada, so more of the risk would be on the higher side.

The inclusion of a start date in the estimation also merits additional comment. For each later year that the project starts construction $1.5 billion ($1.1 to $2.0 billion, in real 2024 CAD) is added to the overall cost. While productivity improvements tend to lower the cost of goods and services, some sectors of the economy (in most countries) do not benefit as much. Illustrative is the Highway, Street and Bridge Construction[^16] in the U.S. Productivity has been trending downward since 2009, and by 2024 was 25 per cent lower than in 2002.[^17] The construction industry in general has not been able to achieve productivity growth similar to that in the rest of the economy. This signals that the start date of construction can be a factor in how much the project will reflect these competing pressures.[^18]

More

No errata have been issued for this publication.

Report an issue with this publication
PDF

Communications

Quotes

  • While Canada’s legislative framework is intended to avoid the major cost-overrun drivers we’ve seen in comparable American and British projects, Canada’s route geography has some significant cost escalators -- most notably tunnelling in and around Montreal, and the complexities of the Canadian Shield portion.

  • Major infrastructure projects involve significant investments and long-term commitments. This report provides Parliament with an independent assessment of the potential construction costs and economic impacts associated with Alto's high-speed rail project, as one of the largest infrastructure projects ever proposed in Canada.

Annette Ryan
Parliamentary Budget Officer

News Release

{"id":99,"created_at":"2026-09-30T13:49:27-04:00","updated_at":"2026-10-01T08:57:02-04:00","slug":"pbo-report-assesses-costs-and-economic-impacts-of-altos-eastern-corridor-high-speed-rail-project-un-rapport-du-bdpb-evalue-les-couts-et-les-retombees-economiques-du-projet-de-train-a-grande-vitesse-dalto-dans-le-corridor-de-lest","title_en":"PBO report assesses costs and economic impacts of Alto\u2019s Eastern Corridor high-speed rail project","title_fr":"Un rapport du BDPB \u00e9value les co\u00fbts et les retomb\u00e9es \u00e9conomiques du projet de train \u00e0 grande vitesse d\u2019Alto dans le corridor de l\u2019Est","body_en":"The Parliamentary Budget Officer (PBO) today released an analysis of the estimated construction costs associated with Alto\u0027s proposed high-speed rail (HSR) project along the Toronto\u2013Qu\u00e9bec City corridor.\n\nThe analysis is based on cost profiles of high-speed rail projects previously undertaken around the world. Basic geographic realities such as the length of the route and the use of tunnels and elevated structures provide strong indicators of overall construction costs in the majority of projects studied \u2013 with the exception of recent projects in the United Kingdom and the United States. In these countries, challenges related to land acquisition, permitting and project delivery led to significantly higher costs.\n\nThe PBO analysed the geography of the route initially proposed by the government, who estimated construction costs between $60 billion and $90 billion. The PBO estimates construction of this route to cost between $75 billion and $113 billion. \n\nThe PBO analysis assumes that planning and construction for the Alto route proceed in a manner consistent with past European high-speed rail projects, rather than the UK or US experience. The government adopted legislation with Bills C-5 and C-15 that aim to mitigate the types of governance, legal and project management risks seen in the UK and US. \n\n\u201c*While Canada\u2019s legislative framework is intended to avoid the major cost-overrun drivers we\u2019ve seen in comparable American and British projects, Canada\u2019s route geography has some significant cost escalators -- most notably tunnelling in and around Montreal, and the complexities of the Canadian Shield portion*,\u201d said Annette Ryan, Parliamentary Budget Officer.\n\nConstruction of the initial Ottawa\u2013Montr\u00e9al segment is expected to provide a modest economic stimulus during the construction phase, currently planned to start in 2029. The PBO estimates that real GDP would increase by approximately $1.8 billion in 2029, rising to $2 billion in 2033, while employment gains would rise from approximately 4,300 jobs in 2029, rising to 9,000 jobs in 2033. \n\n\u0022*Major infrastructure projects involve significant investments and long-term commitments. This report provides Parliament with an independent assessment of the potential construction costs and economic impacts associated with Alto\u0027s high-speed rail project, as one of the largest infrastructure projects ever proposed in Canada*,\u0022 added the Parliamentary Budget Officer.\n\nThis report is the first of a two-part assessment of the viability of the proposed HSR project. A subsequent PBO report will examine whether projected ridership is sufficient to support the system\u2019s operations.","body_fr":"Le Bureau de la directrice parlementaire du budget (BDPB) a publi\u00e9 aujourd\u2019hui une analyse des co\u00fbts de construction estim\u00e9s associ\u00e9s au projet de train \u00e0 grande vitesse (TGV) propos\u00e9 par Alto dans le corridor Toronto-Qu\u00e9bec.\n\nL\u2019analyse s\u2019appuie sur les profils de co\u00fbts de projets de TGV d\u00e9j\u00e0 r\u00e9alis\u00e9s ailleurs dans le monde. Des r\u00e9alit\u00e9s g\u00e9ographiques fondamentales, telles que la longueur du trac\u00e9 et le recours \u00e0 des tunnels et \u00e0 des viaducs, constituent des indicateurs fiables des co\u00fbts globaux de construction dans la majorit\u00e9 des projets \u00e9tudi\u00e9s, \u00e0 l\u2019exception des projets r\u00e9alis\u00e9s r\u00e9cemment au Royaume-Uni et aux \u00c9tats-Unis. Dans ces pays, les difficult\u00e9s li\u00e9es \u00e0 l\u2019expropriation, \u00e0 l\u2019obtention des permis et \u00e0 la mise en \u0153uvre des projets se sont traduites en une augmentation consid\u00e9rable des co\u00fbts.\n\nLe BDPB a analys\u00e9 les caract\u00e9ristiques g\u00e9ographiques du trac\u00e9 initialement propos\u00e9 par le gouvernement, qui avait estim\u00e9 les co\u00fbts de construction entre 60 et 90 milliards de dollars. Le BDPB estime quant \u00e0 lui que la construction de ce trac\u00e9 co\u00fbtera entre 75 et 113 milliards de dollars. \n\nL\u2019analyse du BDPB part du principe que la planification et la construction du trac\u00e9 se d\u00e9rouleront selon un mod\u00e8le similaire \u00e0 celui de projets ant\u00e9rieurs de TGV en Europe, plut\u00f4t que selon les exp\u00e9riences britanniques ou am\u00e9ricaines. Le gouvernement a adopt\u00e9 les projets de loi C-5 et C-15 afin d\u2019att\u00e9nuer les risques li\u00e9s \u00e0 la gouvernance, aux aspects juridiques et \u00e0 la gestion de projet observ\u00e9s au Royaume-Uni et aux \u00c9tats-Unis. \n\n\u00ab Le cadre l\u00e9gislatif canadien vise \u00e0 \u00e9viter les principaux facteurs de d\u00e9passement de co\u00fbts que nous avons observ\u00e9s dans des projets comparables aux \u00c9tats-Unis et au Royaume-Uni, mais les caract\u00e9ristiques g\u00e9ographiques du trac\u00e9 canadien comportent certains facteurs de hausse des co\u00fbts importants \u2014 notamment le creusement de tunnels \u00e0 Montr\u00e9al et dans ses environs, ainsi que les complexit\u00e9s li\u00e9es au tron\u00e7on traversant le Bouclier canadien \u00bb, a expliqu\u00e9 Annette Ryan, directrice parlementaire du budget.\n\nLa construction du premier tron\u00e7on entre Ottawa et Montr\u00e9al devrait g\u00e9n\u00e9rer un effet de relance \u00e9conomique modeste pendant la phase de construction, qui d\u00e9buterait en 2029. Le BDPB a calcul\u00e9 que le PIB r\u00e9el augmenterait d\u2019environ 1,8 milliard de dollars en 2029, pour atteindre 2 milliards de dollars en 2033, tandis que les gains au chapitre des emplois passeraient d\u2019environ 4 300 emplois en 2029 \u00e0 9 000 emplois en 2033. \n\n\u00ab Les grands projets d\u2019infrastructure n\u00e9cessitent des investissements importants et des engagements \u00e0 long terme. Ce rapport fournit au Parlement une \u00e9valuation ind\u00e9pendante des co\u00fbts de construction potentiels et des retomb\u00e9es \u00e9conomiques associ\u00e9es au projet de train \u00e0 grande vitesse d\u2019Alto, qui compte parmi les plus grands projets d\u2019infrastructure jamais propos\u00e9s au Canada \u00bb, a ajout\u00e9 la directrice parlementaire du budget.\n\nIl s\u2019agit de la premi\u00e8re de deux \u00e9valuations portant sur la viabilit\u00e9 du projet de TGV propos\u00e9. Un rapport ult\u00e9rieur du BDPB examinera si l\u2019utilisation pr\u00e9vue est suffisante pour soutenir l\u2019exploitation du r\u00e9seau.","release_date":"2026-10-01T09:00:00-04:00","is_published":"2026-10-01T08:57:02-04:00","appears_on_feed":false,"internal_id":"COM-2627-099","permalinks":{"en":{"website":"https:\/\/www.pbo-dpb.ca\/en\/blog\/news-releases--communiques-de-presse\/pbo-report-assesses-costs-and-economic-impacts-of-altos-eastern-corridor-high-speed-rail-project-un-rapport-du-bdpb-evalue-les-couts-et-les-retombees-economiques-du-projet-de-train-a-grande-vitesse-dalto-dans-le-corridor-de-lest"},"fr":{"website":"https:\/\/www.pbo-dpb.ca\/fr\/blog\/news-releases--communiques-de-presse\/pbo-report-assesses-costs-and-economic-impacts-of-altos-eastern-corridor-high-speed-rail-project-un-rapport-du-bdpb-evalue-les-couts-et-les-retombees-economiques-du-projet-de-train-a-grande-vitesse-dalto-dans-le-corridor-de-lest"}},"pivot":{"publication_id":918,"news_release_id":99}}